【24h】

LARGEST PROJECT ON REPAIR OF PENSTOCKS USING A FIBER REINFORCED POLYMER (FRP) LINER

机译:使用纤维增强聚合物内衬修复牙签的最大项目

获取原文

摘要

This paper describes the repair of a cast-in-place reinforced concrete pipe at the El Encanto power plant outside San Josee, Costa Rica. The penstock that is 5742 feet (1750 m) long with a diameter of 7 ft (2.1 m) brings water from an upstream reservoir along mountainous terrain to the plant. While the water in the pipe is not pressurized, the change in elevation from the reservoir to the turbine complex introduces some pressure in the penstock.In spring 2009, when the construction of the plant was completed, the pipe was filled with water and thousands of small and large leaking holes were observed. As a first attempt, the holes and cracks were sealed with various chemicals and mortars; but when the pipe was filled with water, the cracks opened up again and leaking continued.The repair that was successfully implemented included applying Glass Fiber Reinforced Polymer (GFRP) fabrics on the entire inner surface of the pipe; nearly 150,000 ft~2 (14,000 m~2) of FRP lining was installed, making this the largest reported FRP pipeline retrofit project to date. Among the challenges were the sloping terrain along the mountain and the limited access to the pipeline which consisted of 4 small square ports each 2 ft × 2 ft (600 mm × 600 mm).To save time, all materials were shipped while the design was being finalized. A team of 2 engineers and 4 supervisors were sent to the job site to oversee the installation and train the local crew which consisted of some 40 laborers. The installation of FRP lining and the application of a top coat took only a record 15 days. The repaired pipe was successfully tested in July 2009 and no leaks were observed.
机译:本文介绍了哥斯达黎加圣何塞郊外的El Encanto电厂对现浇钢筋混凝土管道的维修方法。长度为5742英尺(1750 m),直径为7英尺(2.1 m)的压力管道将水从上游水库沿着山地带到植物。尽管管道中的水未加压,但从水库到涡轮机的高度变化却在压力管道中引入了一定的压力。 2009年春季,工厂建设完成后,管道中注满了水,并观察到成千上万个大小不一的泄漏孔。第一次尝试是用各种化学药品和砂浆将孔和裂缝密封起来。但是当管子里装满水时,裂缝再次打开,继续漏水。 成功实施的修复工作包括在管道的整个内表面上应用玻璃纤维增​​强聚合物(GFRP)织物。已安装了将近150,000 ft〜2(14,000 m〜2)的FRP衬里,这是迄今为止最大的FRP管道改造项目。面临的挑战包括沿着山坡的地形以及通往管道的有限通道,管道由4个小方形端口组成,每个端口2英尺×2英尺(600毫米×600毫米)。 为了节省时间,在设计最终定稿时,所有材料都已寄出。由2名工程师和4名主管组成的团队被派往工作现场,以监督安装并培训由40名工人组成的当地工作人员。 FRP衬里的安装和面漆的涂装只花了创纪录的15天。修复后的管道已于2009年7月成功测试,未发现泄漏。

著录项

获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号