首页> 外文会议>International conference on modelling and simulation;ICMS2010 >Prestress-plan Optimization of Spillway Gate Middle-pier of Bakun Hydropower Station in Malaysia
【24h】

Prestress-plan Optimization of Spillway Gate Middle-pier of Bakun Hydropower Station in Malaysia

机译:马来西亚巴昆水电站溢洪道闸门中墩预应力方案优化

获取原文

摘要

Applying the three dimensional finite element method, the bearing properties of a spillway gate middle-pier was calculated. To eliminate the concrete tensile stress in pier support area as large as possible, the effects of anchor-plan of prestress cable, tonnage of cable, spread angle of main cable and arrangement of second cable on the stress distribution and peak value were analyzed. The results of prestress-plan optimization were proposed.
机译:应用三维有限元方法,计算了泄洪闸中墩的承载特性。为了尽可能消除桥墩支护区域内的混凝土拉应力,分析了预应力电缆的锚固方案,电缆的吨位,主电缆的扩展角度和第二电缆的布置对应力分布和峰值的影响。提出了预应力计划优化的结果。