Large Slippage Jig Frame Slipping Technology of Central Station Building of Wuhan New Railway Station

机译:武汉新火车站中央车站大楼大滑移夹具架滑移技术

获取原文

摘要

Steel structure of Wuhan railway station is a hyperboloid large-span syncretic structure. Considering the physical shape of the station and site conditions,large sliding jig and high-altitude in situ erection technology is chosen to be applied in this project after repeatedly comparing with other construction methods. The sliding shall be achieved by hydraulic jack and controlled by a computer simultaneously. The sliding jig is 41.1 meters long,32. 875 meters wide and 52 meters high. A single jig weighs 2740 tons. Remarkable duration management and economic results have been achieved. It is an unprecedented approach both in China and overseas.
机译:武汉火车站的钢结构是双曲面大跨度合一结构。考虑到车站的物理形状和工地条件,在与其他施工方法反复比较后,选择大型滑模和高空原位安装技术。滑动应通过液压千斤顶完成,并由计算机同时控制。滑动夹具长41.1米,32。宽875米,高52米。单个夹具重2740吨。取得了显着的工期管理和经济效果。在中国和海外,这都是前所未有的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号