Analytical modeling of embankment failures, 9th St. E. at I-94, Fargo and West Fargo, ND

机译:北达科他州法戈和西法戈的I-94街第9街,路堤破坏的分析模型

获取原文

摘要

In October of 2007, three of four embankment sideslopes associated with the 9~(th) Street East crossing of I-94 in Fargo and West Fargo, North Dakota, failed.A definitive determination of the failure mechanism was paramount to successful reconstruction - the failure masses could not be effectively removed, relocation was not an option, and it was desired to have the reconstruction work substantially complete for bridge construction in 2009. This was accomplished with analytical models that: (1) replicated the progression of fill-induced pore water pressure and settlement prior to failure, (2) demonstrated a reduction in embankment stability consistent with the timing of the failures, and (3) validated the deformation, hydraulic, and strength parameters required to qualify reconstruction alternatives relative to stability and performance.The embankments were reconstructed with earth and lightweight (foam) fill. Reonstruction instrumentation provided further validation of the analytical models, bringing the project to a successful conclusion.
机译:2007年10月,与北达科他州法戈和西法戈的I-94的第9街东交叉口相关的四个路堤边坡中的三个失败。 最终确定破坏机制是成功重建的关键-无法有效去除破坏团块,不能选择搬迁,并且希望在2009年完成桥梁建设的重建工作。这是通过分析来完成的这些模型:(1)复制了破坏之前填充引起的孔隙水压力和沉降的过程;(2)证明了与破坏时机一致的路堤稳定性降低;(3)验证了变形,水力和相对于稳定性和性能而言,使重建方案合格的强度参数。 路堤用泥土和轻质(泡沫)填料重建。重建仪器为分析模型提供了进一步的验证,使该项目取得了成功的结论。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号