Based on the construction of replacing 75kg/m-heavy rail at Shenchi-Huanghua railroad,Through theoretical analysis and construction practice, Studied and solved the construction technology and construction management program of overall replacing 75kg/m-heavy rail concrete sleeper welded turnout at existing heavy load railway in blocking time by manpower.
机译:在沉黄铁路换重75kg / m重轨施工的基础上,通过理论分析和施工实践,研究解决了目前整体换重75kg / m重轨混凝土轨枕焊接道岔的施工工艺和施工管理方案。重载铁路在人力方面阻碍了时间。