DRAINAGE SERVICES DEPARTMENT WEST KOWLOON DRAINAGE IMPROVEMENT, STAGE 2, PHASE 2, KAITAK TRANSFER SCHEME, DESIGN AND BUILD CONTRACT

机译:九龙西渠务署渠务改善工程第2期第2期,凯塔克(KAITAK)转运计划,设计及建造合约

获取原文

摘要

The Drainage Services Department (DSD) of the Hong Kong SAR Government commissioned the design and construction of the West Kowloon Drainage Improvement, Stage 2, Phase 2, Kai Tak Transfer Scheme (KTTS) project in 2000 to relieve potential flooding in Mong Kok caused by the insufficient capacity of the existing storm water drainage system. The KTTS involves construction of a 1.5km, 4.4m drainage tunnel and a 450m long box culvert, running from Waterloo Road near Hereford Road to the existing Kai Tak Nullah in San Po Kong. This paper describes the design and construction of; the bored tunnel through both hard rock and soft ground using a slurry Tunnel Boring Machine (TBM), six associated access shafts, a connection structure at Waterloo Road and the box culvert connecting the bored tunnel to the outfall at Kai Tak nullah. Details will be provided on the contractor's alternative designs adopted during the contract including the use of fibre reinforced shotcrete as one-pass temporary and permanent support for three of the shafts and modifications to the Engineer's design for the box culvert structure.
机译:香港特别行政区政府渠务署于2000年委托设计及建造西九龙排水改善工程第二期,第二期,启德转运计划(KTTS)工程,以纾缓旺角可能引致的洪灾。现有雨水排放系统容量不足。九龙尖沙咀运输站将兴建一条长1.5公里,4.4m的排水隧道及一条450m长的箱形涵洞,该涵洞由赫里福德道附近的窝打老道至新蒲岗现有的启德明渠。本文介绍了其设计与建造;使用泥浆隧道掘进机(TBM),六个相关的通道井,位于窝打老道的连接结构和将涵洞隧道连接至启德明渠出水口的箱形涵洞,通过硬岩和软土地层的掘进隧道。将提供承包商在合同期间采用的替代设计的详细信息,包括使用纤维增强喷浆混凝土作为对三个竖井的一过性临时和永久支撑,以及对盒涵结构的工程师设计的修改。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号