NPP POWER UPRATING IN BELGIUM THE DOEL3 AND TIHANGE 1 EXPERIENCE

机译:比利时Doel3和TIHANGE 1的NPP功率提升

获取原文

摘要

The three steam generators at Doel 3 nuclear powerplant were affected by primary side stress corrosion crackingas early as 1983, after a single year of operation. Electrabel,the owner of Doel 3, decided in 1989 to replace the steamgenerators and in parallel an uprating feasibility study waslaunched by Belgatom. During the summer of 1993, thesteam generators were installed and in the beginning ofSeptember 1993 the plant was operated at a powercorresponding to 110% of the initial design power.In 1991, SEMO the owner of the Tihange 1 power plantasked EdF and Belgatom to evaluate the achievable upratingin case of steam generator replacement. The steam generatormanufacturing contract was awarded in March 92 and anuprated power level of 105% of initial design level wasreached in September 95. Final core uprated power level of108% will be reached during the second transition cycle aftera complete unload of the old limiting fuel.Belgatom, acting on behalf of the Utilities, tookresponsibility for the overall project management and wasalso in charge of the uprating study programme. Part of thestudies was performed by Belgatom, part has beensubcontracted to NSSS suppliers who were not in all casesthe steam generators suppliers. This paper gives an overviewof the two projects and presents the main milestones ofthem. Both projects have been divided in three phases : aconceptual phase, a detailed design phase and animplementation phase. The paper presents shortly twoBelgatom methodologies that were developed and appliedduring these two projects.
机译:在运行一年之后,Doel 3核电站的三台蒸汽发生器早在1983年就受到一次侧应力腐蚀开裂的影响。 Doel 3的所有者Electrabel于1989年决定更换蒸汽发生器,与此同时Belgatom发起了一项升级可行性研究。在1993年夏季安装了蒸汽发生器,并在1993年9月初以相当于初始设计功率110%的功率运行了该工厂。1991年,Tihange 1功率计划的所有者SEMO责成EdF和Belgatom对其进行评估。在更换蒸汽发生器的情况下可以实现升级。蒸汽发生器制造合同于92年3月签订,在95年9月达到了初始设计水平的105%的提升功率水平。在完全卸载旧的极限燃料后的第二个过渡周期中,最终核心提升了108%的功率水平。Belgatom代表公用事业公司,负责整体项目管理,还负责升级学习计划。部分研究由Belgatom执行,部分研究已分包给NSSS供应商,而这些供应商并非在所有情况下都是蒸汽发生器供应商。本文概述了这两个项目,并提出了它们的主要里程碑。两个项目都分为三个阶段:概念阶段,详细设计阶段和实施阶段。本文简要介绍了在这两个项目中开发并应用的两种Belatom方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号