Influence on High-Speed Railway Bridge Caused by Shield Tunneling in Sandy Pebble Stratum and Its Controlling Technologies

机译:砂卵石地层盾构施工对高速铁路桥梁的影响及其控制技术

获取原文
获取原文并翻译 | 示例

摘要

During the construction of interval tunnel from the Tianqiao Station to the outside of Yongdingmen Station of Metro Line 8 in Beijing City, the shield machine will have to pass beneath an existing bridge. On top of the bridge, it is the Beijing-Tianjin intercity railway and the Beijing-Shanghai high-speed railway. At the project worksite, sand and gravel is the main component of ground formation. The stratum is a typical unstable one, so it is easy to induce the excavation face instability and ground subsidence or even collapse during the process of shield tunneling, which will inevitably affect the safe operation of the above railway bridge as the highspeed train has extremely strict requirements on track smoothness. Therefore, the risk of shield crossing construction is rather high. In this paper, the impact of tunnel excavation on the stress and deformation of the bridge structure as well as ground settlement, distribution of pore water pressure caused by shield tunneling were analyzed by means of three-dimensional numerical simulation. Furthermore, a series of countermeasures and monitoring schemes were proposed to ensure the safe operation of bridge before and after the shield crossing construction. The research results can not only guide the construction of this project, but also provide some reference for other similar issues.
机译:在北京地铁8号线天桥站至永定门站外的区间隧道施工过程中,盾构机将必须通过现有桥梁下方。桥顶是京津城际铁路​​和京沪高铁。在项目工地,沙子和砾石是地层的主要组成部分。地层是典型的不稳定地层,在盾构施工过程中容易引起开挖面的不稳定性和地面的沉降甚至塌陷,这对高速铁路极为严格,不可避免地影响了上述铁路桥梁的安全运行。轨道平整度要求。因此,盾构穿越施工的风险很高。本文通过三维数值模拟,分析了隧道开挖对桥梁结构的应力和变形以及盾构施工引起的地面沉降,孔隙水压力分布的影响。并提出了一系列对策和监测方案,以确保盾构穿越施工前后桥梁的安全运行。研究成果不仅可以指导本项目的建设,还可以为其他类似问题提供参考。

著录项

  • 来源
  • 会议地点 Beijing(CN)
  • 作者单位

    College of Transportation Engineering, Tongji Univ., 201804, Shanghai, China;

    College of Transportation Engineering, Tongji Univ., 201804, Shanghai, China;

    Five Iron Group Electric Service City Link Engineering Co. Ltd., 410205, Changsha, Hunan, China;

    Five Iron Group Electric Service City Link Engineering Co. Ltd., 410205, Changsha, Hunan, China;

  • 会议组织
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号