In standby mode, PLTG Gilimanuk still requires electricity consumption for its own usage for both generator and non-power plant needs. The use of PV can be an alternative to meet the need for electricity consumption for own use. Installation of PV will reduce the operational costs for the fulfilment of electricity needs for own use. In this paper, discounted cashflow (DCF) method is used to analyse whether the installation of PV is feasible and could be used as an alternative of electricity energy source for own use at PLTG Gilimanuk.
机译:在待机模式下,PLTG Gilimanuk仍然需要电力消耗,以满足发电机和非电厂的需求。使用PV可以替代满足自己使用的电力消耗的需求。安装光伏发电将降低满足自用电力需求的运营成本。本文采用折现现金流(DCF)方法来分析光伏装置的安装是否可行,并可以作为PLTG Gilimanuk自己使用的替代能源。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号