首页> 外文会议>HLW, LLW, mixed wastes and environmental restoration - working towards a cleaner environment >LESSONS-LEARNED FROM THE 20-YEAR URANIUM MILL TAILINGS REMEDIAL ACTION SURFACE PROJECT
【24h】

LESSONS-LEARNED FROM THE 20-YEAR URANIUM MILL TAILINGS REMEDIAL ACTION SURFACE PROJECT

机译:从20年铀矿尾矿修复行动表面项目中学到的经验教训

获取原文
获取原文并翻译 | 示例

摘要

In 1978 Congress directed the Department of Energy to clean up 22 inactive uranium processing sites.rnIn late 1998 the Department of Energy’s Uranium Mill Tailings Remedial Action (UMTRA) SurfacernProject completed the cleanup of the last of these 22 sites and the last of more than 5,300 associatedrnvicinity properties. The Project disposed of more than 40 million cubic yards of material, which isrnabout 80 percent of the volume to be cleaned up by the Department’s Environmental ManagementrnProgram.rnAlthough, the tailings contained small amounts of radioactivity, they posed a real risk because theyrnwere located at numerous facilities that were not under DOE control. This marks the completion ofrnthe first major cleanup program by the Department of Energy’s Environmental Management Program.rnOver the 20-year span of the Project, important technical and management lessons have been learnedrnthat can be applied to other cleanup programs. The Project provides many valuable case studies fromrnthe variety of situations addressed over the past 20 years.
机译:1978年,国会指示能源部清理22个闲置的铀加工场。1998年末,能源部的铀厂尾矿治理行动(UMTRA)SurfacernProject完成了对这22个场址和最后5,300多个场址的清理。相关的性质。该项目处置了超过4000万立方码的材料,约占美国能源部环境管理计划清理量的80%。尽管尾矿中含有少量放射性,但它们构成了真正的风险,因为它们位于多个地方不受DOE控制的设施。这标志着能源部环境管理计划完成了第一个主要的清理计划。在该项目的20年中,已经吸取了重要的技术和管理经验教训,这些经验教训可应用于其他清理计划。该项目提供了来自过去20年中各种情况的许多有价值的案例研究。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号