Post-Construction Landfill Liner Failure and Lessons Learned

机译:施工后垃圾填埋场衬砌的失败和经验教训

获取原文
获取原文并翻译 | 示例

摘要

A relatively small rural landfill was designed with a PVC/GCL composite liner system overlain by 300 mm of gravel. Onernend of the project contained a slope having an inclination at 4(H):1(V) for a length of approximately 58 m. Three monthsrnafter construction the PVC liner had ripped along the crest of the slope, and the gravel and PVC had slid on top of thernGCL along the entire slope length. The GCL was exposed about half way down the slope. The failing interface wasrnclearly between the PVC and the GCL. The lessons learned from this project were (a) to conduct slope stability testingrnand analyses for interim and construction conditions in addition to final fill conditions, and (b) interface direct shearrntesting should have interfaces sprayed with water during the setup, and not just count on flooded conditions to allowrnwater to travel to the interface. Neither of these lessons is particularly new to the industry, showing the value of having arnproject peer-reviewed by designers experienced with the nuances of geosynthetics design and construction.
机译:设计了一个相对较小的农村垃圾填埋场,其PVC / GCL复合衬砌系统覆盖了300毫米的砾石。该项目的Onernend包含一个坡度为4(H):1(V)的斜坡,长度约为58 m。施工后三个月,PVC衬里已沿着斜坡的顶部撕裂,砾石和PVC已沿着整个斜坡长度在GCL顶部滑动。 GCL暴露在斜坡下方约一半处。 PVC和GCL之间的接口故障很明显。从该项目中吸取的教训是:(a)进行边坡稳定性测试并分析最终填充条件之外的临时和施工条件;(b)界面直接抗剪测试应在设置过程中向界面喷水,而不仅仅是依靠淹没条件使地下水流到界面。这两个课程都不是行业中特别新鲜的课程,它显示了对具有土工合成材料设计和构造细微差别的设计师进行arnproject同行评审的价值。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号