The Annapolis Group engaged Hatch Ltd to undertake a condition assessment and dam safety review of the Kearney Lake Dam on the Paper Mill River in Bedford, Nova Scotia. The site consisted of a concrete overflow structure and a low wing dam near the main dam. It was found that rehabilitation work was required to address deterioration of the concrete overflow dam and to improve the stability of the structure. The consequence assessment found that the required design flood (IDF) was the Probable Maximum Flood, considerably larger than the capacity of the existing structure, which was estimated at less than the 1/100 Annual Exceedance Probability (AEP) event.This paper presents the unique approach that was undertaken in the rehabilitation work to address the owner's concern that the changes to the dam to handle the design flood could not appear to significantly alter or enlarge the footprint of the existing dam, and the rehabilitated structure had to blend in with the landscape. The approach taken was to construct a buried weir at a location downstream of the existing wing dam which would link the dam abutment to high ground. The existing dam was modified so that most floods (up to about 1/1000 AEP) would be contained within the existing abutments, and extreme floods (up to the design flood) would go over the buried weir and down an old channel.
机译:安纳波利斯集团委托Hatch Ltd对新斯科舍省贝德福德的造纸厂河上的科尔尼湖大坝​​进行状况评估和大坝安全审查。该地点由混凝土溢流结构和主坝附近的低翼坝组成。人们发现,需要进行修复工作来解决混凝土溢流坝的恶化和提高结构的稳定性。结果评估发现,所需的设计洪水(IDF)是“可能的最大洪水”,大大大于现有结构的容量,后者估计小于1/100年度超标概率(AEP)事件。在修复工作中采取的独特方法来解决所有者的担忧,即为应对设计洪水而对大坝进行的变更似乎不会显着改变或扩大现有大坝的占地面积,而修复后的结构必须与大坝相融合景观。采取的方法是在现有翼坝下游的位置建造一个埋入式堰,将坝基与高地连接起来。对现有大坝进行了修改,以使大多数洪水(最高约1/1000 AEP)将包含在现有桥台中,而极端洪水(最高为设计洪水)将越过掩埋堰并沿着旧河道下降。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号