GROUND-BORNE VIBRATION MEASUREMENTS OF DRILL?AND-BLAST EXCAVATION, SHEET PILE INSTALLATION, AND TBM EXCAVATION IN SANDSTONE AND SHALE MéLANGE

机译:砂岩和页岩黑土钻爆开挖,板桩安装和TBM开挖的地下振动测量

获取原文
获取原文并翻译 | 示例

摘要

Ground-borne vibration generated by construction activities is often a significantrnpublic concern during the planning and construction phases of a project. Publishedrnvibration data for various excavation methods are limited and include projects constructedrnin different geologic materials that range from soft ground to hard rock, and itrnhas been shown that ground-borne vibration levels are sensitive to the type of geology.rnGround-borne vibration measurements conducted during drill-and-blast excavation,rnsheet pile installation, and tunnel boring machine (TBM) excavation at the New CrystalrnSprings Bypass Tunnel Project in San Mateo, California, are reviewed. This projectrnwas excavated in Franciscan Complex rock, which is a highly heterogeneous mixturernof harder sandstone and a weaker, sheared shale mélange matrix, also referred tornas “block in matrix” rock. The proximity of the tunnel and access shafts to residentialrnhomes, as well as existing water supply lifelines, prompted strict limitations on noisernand vibration for construction activities.
机译:在项目的规划和施工阶段,施工活动产生的地面传播振动通常是引起公众广泛关注的问题。公开的各种开挖方法的振动数据是有限的,并且包括在从软土地到硬岩石的不同地质材料中建造的项目,并且已经表明,地面传播的振动水平对地质类型敏感。钻进期间进行的地面传播的振动测量在加利福尼亚州圣马特奥市的新CrystalrnSprings绕行隧道项目中,进行了爆破开挖,rnsheet桩安装和隧道掘进机(TBM)开挖的审查。该项目是在方济各会综合体岩石中开挖的,该岩石是高度异质的混合物,包括较硬的砂岩和较弱的剪切页岩混杂岩基质,也称为“基质中的块状”岩石。隧道和出入口竖井靠近居民住宅,以及现有的供水生命线,对建筑活动的噪声和振动提出了严格的限制。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号